PD North
Project Details North
-
Substantially Completed Projects In North +
Projects Date of
CommDate of
CompCA Amount Dargai-Chakdara Sec Jun-06 Jul-10 617.469 Takht Bhai-Sher Garh Rd Jun-06 May-13 201.975 Timergara-Akhagram Sec Jun-06 Nov-12 510.855 Timergara-Munda Road Sep-08 Dec-10 592.208 Kanju-Sambat Road Apr-11 Dec-13 579.6 Const of APSAC May-11 Jun-13 718 CKSKS(NH) Cadet College Jul-06 Jun-12 465.2 AJK Phase-I Jun-06 Dec-11 647.805 AJK Phase-I Ext Svcs Jun-08 Dec-11 76.135 AJK Phase-II Jul-07 Dec-11 860.444 AJK Phase-III Jun-08 Dec-11 562.454 AJK Bdry Wall & Fence Jul-09 Dec-11 42.515 Re-Engineering Works DHA I May-06 Feb-11 2105.25 Dualization of Golra Road May-11 Jun-12 238 Flyover At Chandni Chowk Nov-11 Jun-12 993.32 Rehabilitation of POF WAH Rds May-12 Nov-13 273.266 W/I of Churr Chowk Aug-12 Mar-13 218.29 Bilal Umer Shaheed Colony Feb-12 May-12 108.27 Rawalpindi Road Rehabilitation Mar-10 Feb-11 642.065 MES Jan-10 Nov-11 573.54 Convoy Route Proj Aug-11 Oct-13 902.79 Rawalpindi Dev Authority Feb-10 Jun-11 183.85 OFC (FWOCP) Ph I Jul-07 Jan-11 540 Govt Degree College Manghot Apr-12 Jun-13 257 Military College Jehlum Jul-13 Apr-14 63.686 Jhika Gali Ph I&II Apr-12 Dec-13 1153 Fly over at 6th Rd Sep-12 Sep-13 772.93 Flyover at Pirwadhae Mor Oct-12 Sep-13 1029.44 Kallar Kahar To Choa Saidan Shah Rd Jan-13 Dec-13 536.34 Mobilink Connectivity May-11 May-12 331.21 Thakot Proj Feb-05 Oct-05 223 Br Over Nala Lai Jul-11 Nov-12 210 Dualization of Road (Alshifa To Amar Chowk ) May-12 Dec-13 300 Widening of Railway Br at Marrir Chowk Nov-12 Dec-13 547.5 Construction of Operation Theater at CMH Rawalpindi – P0204 Sep-04 Jun-07 153 UBM NLC Gujrunwala Cantt Sep-11 May-12 183 Metro Bus Pkg II(Rwp Sec) March-14 March-15 4,485 Const of Army Special Education Academy Nov-13 Aug-14 78 -
Ongoing Projects - North +
Projects Start Date End Date %Progress
Aug-16Scope
(Mn)Revenue
Aug-16
(Mn)Dualization of Mandra Chakwal Rd (63 km) Jun-14 Dec-16 30.68% 6,681 2,054.13 Metro Bus Project Isb (Pkg -II) Apr-14 Oct-16 100.70% 6,499 6,567.18 Dualization of Sohawa Chakwal Rd (65 km) Jun-15 Dec-17 4.51% 7,120 321.43 Office Bldg Complex (Q Proj) Jun-11 Aug-16 99.61% 3,984 3,973.48 Ext Svcs MH Proj Rwp Oct-13 Dec-16 69.93% 1,026 719.08 Rehabilitation of Rd from Lower Topa to Danna to Patriata Apr-14 Oct-16 89.87% 271 232.52 Koral Chowk to Airport Rd Proj Jun-15 Sep-16 74.75% 427 319.13 Const Works at PMA Kakul Aug-15 Sep-16 93.98% 484 454.96 Rehabilitation of Rd from Bansra gali to Lawrence College to Jhika gali Apr-14 Dec-16 103.75% 405 421.69 Mianwali-Jand Rd Proj Oct-12 Dec-16 90.55% 672 610.08 DHA Ph-IV, Isb Feb-14 Jan-17 38.61% 3,325 1,286.87 Sowan Bridge Proj (900 m) Nov-13 Sep-16 96.23% 746 719.56 Sanni Nullah Bridge Proj (300 m) May-14 Dec-16 65.41% 445 292.23 Kahuta to Panjar Azad Pattan Rd Proj (18 km) Jan-16 Jan-17 13.21% 592 78.23 Const of Main Link Rd to NIIA, Isb (5.1 km) May-16 Feb-17 6.10% 2,283 139.56
- 1